The Flood Alleviation Scheme
The scheme can be divided into 5 components:
- A new kerb headwall and 300mm diameter pipe was installed where the small watercourse flowing from the area of houses around Springfield Road flows under the footpath leading to the reservoir.
- The 150mm diameter drain running underneath Reservoir Road was replaced with a 300mm diameter pipe and new 600mm wide gully and kerb headwall.
- A new Aco drain was installed across the footpath leading to Reservoir Road, as well as new 600mm wide gullies and associated cross-drain along Reservoir Road.
- The 750mm diameter culvert was extended, a new headwall and grid were installed, and an associated hardstanding area was constructed at the Y-junction between both Reservoir Roads.
- New 600mm wide gullies were installed further south along Reservoir Road.
The work was completed between 31st January and 04th March 2022.
Benefit
This scheme now provides a higher level of flood protection for 25 residential properties and 1 business and enhances the amenity of the recreational site.
Funding
The improvement works cost a total of £45,445.
£38,628.25 of funding was awarded to Carmarthenshire County Council from the Welsh Government.
£6,816.75 was contributed by Carmarthenshire County Council.